Main Street Construction Project - Update on October 13, 2018

Construction is progressing well with a completion date of October 31, 2018. Interlock is expected to be finished by October 19, 2018.

The construction team continues to meet with the engineer and municipal staff every two weeks to discuss any issues. These meetings are generally followed by a “walk about” of the site to give staff and engineer first-hand understanding of the progress.

All asphalt work should be completed by October 31th, 2018, possibly earlier if the weather cooperates. Communication with CN Rail will determine when construction near the rail tracks can be done. Canada Post deliveries have been re-routed through the municipal parking lot for the time being.

Minutes prior to 2018 may be requested at This e-mail address is being protected from spambots. You need JavaScript enabled to view it .

 

September 18, 2018 Medical Centre Agenda Complete Package

August 23, 2018 Medical Centre Minutes

August 23, 2018 Medical Centre Agenda Complete Package

May 28, 2018 Med Centre Minutes

May 28, 2018 Medical Centre Agenda Complete Package

April 17, 2018 Medical Centre Minutes

April 17, 2018 Medical Centre Minutes Closed

April 17, 2018 Agenda Complete Pkg

March 20, 2018 Med Centre Minutes

March 20, 2018 Closed Minutes

March 20, 2018 Medical Centre Agenda Complete Package

February 20, 2018 Med Centre Agenda Complete Pkg

February 20, 2018 Medical Centre Minutes Closed

February 20, 2018 Medical Centre Minutes

January 16, 2018 Med Centre Agenda Complete Pkg

January 16, 2018 Medical Centre Minutes Closed

January 16, 2018 Medical Centre Minutes

Best online roulette for money https://onlineroulette.money/